Guidance on floor mounted magnetic strip laying for Zowell VNA forklifts
1. Ground cleaning: Clean the ground, remove debris and dust, wait for the ground to dry before proceeding to the next step.
2. Taking the middle line: According to the shelf column, scribe the line to find the center. Measure the distance from the shelf, column to column in the aisle, and then take the center and scribe the line.
3. Laying the magnetic strip: the magnetic strip will be placed in accordance with the drawn center line, the magnetic strip needs to be laid flat, not bent, distorted. The gap between the magnetic strips should be less than 2mm, and the magnetic strips should be protected by a special protective tape.